On Tuesday 20 October 2026 the High Court quashed the Council’s first permission for the Christ’s College library, of 7 November 2025, on all four grounds of our claim.

The Council’s documents

The conservation officer’s response, 18 September 2025

PDF · 5 pages · Primary source · The text below is the PDF’s own text, page by page

The Council’s conservation officer’s response on application 25/02161/FUL, 18 September 2025 (5 pages; register document 7370966). It first set the harm at "the lower end" and found that the works "would help to secure the building’s optimum viable use", the finding the 2025 report carried into its balance and the third ground of the judicial review.

Download the original PDF · Back to Documents

The document in full

Open the original PDF

Page 1

APPLICATION - CONSULTATION RESPONSE Consultee: Reference Number: Proposal:

Site Address:

Case Officer: Responding Officer: Date:

BNE - Conservation 25/02161/FUL_&_25/02162/LBC Demolition of 1970s library and replacement with new library and social and study spaces and including re-provision of bridge to the Bodley Library. Alterations to kitchen, Upper Hall and adjacent areas including new plant, access improvements and alterations to WC provision in the SE range of Second Court. Re-landscaping of Bath Court and ancillary works. Installation of temporary kitchen and dining facility in Second Court for the duration of the works. Christs College, Christs College Library St Andrews Street Cambridge Cambridgeshire CB2 3BU Dominic Bush Paul Robertshaw 18.09.25

☒ No objection ☐ Amendments are / Further information is required ☐ Object for the following reasons: ☐ Outside remit of this consultee’s specialism Documents Reviewed •

Revised plans

Suggested Conditions

Code

Page 2

Protection and Support

CS04AP

Salvage and reuse of materials

CS28AS

New walls

CS39AS

Joinery details

CS09AS

Timber frame repairs

CS12AC

Rainwater Goods

CS49AS

Materials

Bespoke

No development shall take place above ground level, except for demolition, until details of all the materials for the external surfaces of buildings and ground surfaces to be used in the construction of the development have been submitted to and approved in writing by the local planning authority. Samples of the materials shall be made available on site for inspection by officers. Development shall be carried out in accordance with the approved details. Reason: To avoid harm to the special interest of the listed building (Cambridge Local Plan 2018, policy 61). Precise details No work shall commence on the relevant areas until details of the following items have been submitted for the prior, written approval of the Local Planning Authority: (a) Details of first floor landing alterations including timber samples, to be inspected and agreed on site with the conservation officer, and junctions with new work and existing panelling (b) Details of alterations to panelling (c) Details of photovoltaic panels showing relationship to roof (d) Details of vents, flues and extracts (e) Details of signage (f) Details of external lighting (g) Details of gates and railings (h) Details of structural alterations to listed building

CS03AP insert

Page 3

The works shall be carried out in accordance with the agreed details. Reason: To avoid harm to the special interest of the listed building (Cambridge Local Plan 2018, policy 61). Recording of building post-work

GS05AC insert

The listed building shall be fully recorded before and during works by means of drawings, photographs and written report to Level 2 as set out in Historic England's Understanding Historic Buildings: A Guide to Good Recording Practice 2016. Copies of the final, completed report shall be submitted to the Local Planning Authority and the County Historic Environment Record within one year of the completion of works. Reason: To ensure that the listed building is properly recorded both before and during works. Hard and soft landscaping

SL10CS

Background information /additional comments: Heritage assets See comments dated 11.07.25. Two aspects of the proposals have been revised in response to earlier comments. The chimneys have been reduced in height by approximately 900mm with the result they are no longer visible from First Court other than the slightest glimpse from the northern edge. The design of the chimneys has also been refined to add vertical slots that have a functional role and assist in breaking down their perceived mass. The revised design has satisfactorily addressed the previous concerns in relation to the setting of First Court and can therefore be supported.

Page 4

As previously stated, the building is large in relation to its plot, with the change in scale between the proposed stair tower and the southern end of the Bodley Library being particularly striking. This is considered to result in a degree of harm. The shorter chimneys emphasise the stair’s relative size in some local views as there is no longer the sense of stepping up in height. However, the principle and scale of the stair tower is accepted, and it would not be exceptional in relation to other taller elements within the college and neighbouring buildings. The set back and lightness of the design succeed in partly mitigating its visual impact. It is considered the proposed elevation to Christ’s Lane represents an enhancement to the conservation area due to the improved quality of the proposed design and materials as well as the new view into Bath Court. The overall scale of the building, including the stair tower, is not considered inappropriate or harmful in relation the college and conservation area more widely, and there are larger buildings in the immediate area. The impact to the setting of the listed building in Bath Court is not a concern due the secondary nature of this elevation and the notable improvements proposed to the current poor-quality building and external landscape. The kitchen plan has been revised to incorporate the wash up area, with the old buttery remaining as offices. This addresses earlier concerns, and the revised proposal is considered acceptable with no harm caused. See earlier comments in respect of the remaining internal works, which continue to be supported subject to detail. Summary It is considered the proposal would cause harm to the setting and significance of the listed building. The harm would be less than substantial at the lower end of the scale and therefore NPPF paragraph 215 is engaged. It is considered the harm has been clearly and convincingly justified as required by paragraph 213. The proposal includes public benefits in the form of heritage benefits and the works overall would help to secure the building’s optimum viable use.

Page 5

It is considered that the proposal would preserve the character and appearance of the conservation area for the reasons set out above. The proposals would meet the requirements of Local Plan policy 58 and 61.

Open the original PDF

The first permission is quashed. The second is frozen.

On Tuesday 20 October 2026 the High Court quashed the first approval, 25/02161/FUL, on all four grounds of our claim. The Secretary of State has frozen the permission. On 13 October she directed the Council not to grant it without her authorisation while she considers whether to call the application in, six days after the identical application 26/02109/FUL was controversially approved. If you would like to support a call in, write to us and we will tell you how.